7-Month Kitchen Remodeling Diary

Read the remodeling diary of a homeowner who has been through the kitchen remodeling process and survived. You'll likely pick up tips on how to think ahead -- and what you might avoid.
Martha's Kitchen Diary: Sept. - Nov

September 1-21
Secure loan from bank and commission plan from kitchen designer. Order cabinets from home center.

October 8-15
Cabinets arrive-six missing, two damaged. (Learn one of the first lessons of a remodel: patience.) Send the damaged ones back and store others in the garage. Reorders arrive eventually.

October 16-17
Demolition begins. Husband David and his parents tear out plaster walls and floors. Contractor installs new French door. David and his dad assemble cabinets in the garage.

November 4
Insulate walls and ceiling. Buy unfinished red oak flooring at home center so it can acclimate in the house for the required 72 hours before installation. Rent nailers from home center.

November 6-7
Install wood flooring in kitchen. Glad David's friend can help because it's definitely a project for two people. Save about $1,000 in labor.

November 8-12
The longest week ever. Drywallers arrive. Dust was everywhere. Once they were done, you could actually see the new space taking shape!

November 12-13
Couldn't wait to see the green paint color our designer picked. So much energy we paint seven hours straight two days in a row. The whole house seemed to change.

Continued on page 2:  Martha's Kitchen Diary: Nov. - March

 

Comments

Comments ( 0 )
2300000707

Add your comment

You must be logged in to leave a comment. Register | Log In
Kitchen Hot List
Ceramic and porcelain mosaic tile

See our top picks from the Kitchen and Bath Industry Show


ADVERTISER